New Oxford Street works underway

Work started on the area around New Oxford Street on the 19th March and is expected to be completed by the end of August. Our contractors VolkerHighways will be working on both sides of New Oxford Street, between Tottenham Court Road and Dyott Street as well as the Earnshaw Junction.

We will be taking up and replacing the paving with granite slabs as well as taking up and re-laying some of the kerbs. We will also be completing the upgrade to the Earnshaw Street junction traffic signals and installing the new pedestrian crossing.

We will work in small sections to maintain pedestrian access along the footways while also maintaining access to shop entrances and other doorways.

Buses will continue to use New Oxford Street in both directions during the works, although it will be necessary to suspend bus stops when working close to them. Replacement stops will be provided nearby.

Explore the current programme

16th May – 14th July, repave the northern side between Bainbridge Street and Dyott Street, working from Bainbridge to Dyott
11th June – 23rd June, repave the northern side between Tottenham Court Road and Bainbridge Street
18th – 30th June, cabling the new signals at the Earnshaw Street junction and bringing the new pedestrian crossing on the east side into use.
25th June – 30th June, raising the road to footway level across the Bainbridge Street junction.